% Earliest project completion wrt. precedence relations: 82
|
|
% Used factor: 1.000000
|
|
t_max = 82;
|
|
n_res = 4;
|
|
cost = [6, 7, 8, 7];
|
|
n_tasks = 60;
|
|
dur = [7, 2, 4, 2, 4, 2, 1, 2, 7, 9, 1, 3, 6, 8, 9, 7, 9, 1, 4, 4, 6, 1, 9, 1, 6, 3, 10, 5, 8, 3, 7, 5, 7, 2, 10, 6, 3, 10, 8, 2, 7, 4, 10, 2, 1, 4, 6, 3, 2, 8, 2, 7, 7, 6, 9, 7, 8, 7, 5, 8];
|
|
succ = [{5, 13, 24}, {4, 6, 7}, {12, 19, 21}, {8, 16, 37}, {8, 40, 50}, {20, 29, 58}, {9, 10, 15}, {26, 47, 53}, {11, 14, 18}, {31}, {17, 48}, {25, 27, 42}, {18, 23, 25}, {31, 43, 52}, {23, 28, 32}, {18, 21, 41}, {22, 23, 31}, {32, 36, 44}, {27}, {26, 33, 41}, {42, 59}, {24, 29, 34}, {33, 39, 43}, {26, 33, 36}, {29, 48, 57}, {39, 45, 55}, {30, 32, 46}, {38, 40, 48}, {54}, {35, 45, 47}, {37, 51, 53}, {43, 47, 49}, {38, 42}, {37, 41, 44}, {36, 50, 52}, {39, 58}, {38, 40}, {46}, {59}, {56}, {51}, {46, 54}, {45}, {49, 57}, {60}, {55}, {51, 52, 55}, {49}, {50}, {53}, {54, 59}, {56}, {58}, {60}, {56}, {57}, {60}, {}, {}, {}];
|
|
rr = [| 1, 9, 2, 9, 7, 3, 6, 2, 7, 3, 8, 9, 10, 10, 1, 9, 6, 2, 5, 4, 5, 2, 8, 7, 9, 4, 4, 6, 5, 4, 4, 2, 5, 4, 8, 4, 3, 1, 2, 5, 1, 10, 9, 1, 10, 10, 10, 8, 2, 1, 7, 8, 2, 10, 9, 1, 2, 3, 6, 7
|
|
| 1, 8, 8, 2, 6, 8, 4, 4, 2, 5, 4, 7, 9, 7, 4, 2, 2, 2, 7, 1, 8, 10, 1, 10, 9, 4, 3, 9, 9, 8, 2, 5, 8, 5, 10, 1, 10, 7, 5, 7, 7, 1, 7, 2, 10, 4, 3, 8, 2, 9, 5, 9, 5, 2, 3, 7, 3, 8, 7, 3
|
|
| 3, 10, 8, 9, 7, 7, 3, 4, 5, 3, 8, 3, 4, 10, 1, 4, 8, 6, 4, 2, 7, 8, 3, 3, 5, 8, 8, 10, 4, 3, 5, 3, 5, 2, 2, 1, 8, 7, 8, 6, 6, 5, 1, 5, 5, 5, 3, 2, 3, 3, 1, 5, 6, 7, 9, 3, 3, 7, 3, 4
|
|
| 2, 7, 10, 4, 1, 5, 1, 10, 1, 2, 3, 6, 1, 1, 3, 10, 10, 6, 3, 8, 3, 5, 2, 2, 9, 1, 7, 2, 9, 10, 5, 5, 9, 4, 7, 3, 6, 5, 6, 9, 5, 4, 5, 7, 6, 1, 3, 3, 5, 1, 4, 5, 3, 7, 10, 10, 8, 8, 8, 4
|
|
|];
|